Baile na nGall Waterford Sewer Network Upgrade

David Walsh Civil Engineering Ltd. was awarded this contract under a Capital Framework on behalf of Uisce Éireann.  Construction commenced in January 2025 and is due for completion in Q3 2026.

The Project includes the Design and Build of the following:

  • New An Móta Pumping Station and emergency storage tank
  • New Baile na nGall Pumping station and emergency storage tank
  • New Baile na nGall WwTP Pumping station and Stormwater holding tank
  • Rising main from the new An Móta PS and from the new Baile na nGall PS to connect the existing gravity network.
  • Upsizing and re-laying of the existing gravity network.

The project included all Civil, Building and MEICA works including; new control and welfare building, new toilet block construction, retaining wall construction, inlet screening and pumping, flow measurement, provision of ESB power supply and provision of SCADA/Telemetry.